The dredge D6 alongside the wharf in Saulnierville with Atlantic Tamarack alongside this evening. Both buckets and the two dump scows HD-8 and HD-9 are now gone. Dredging activities were completed earlier in the week.
Commdive II has the first piling ready to go. All pilings have been moved from the parking lot to the wharf for easier installation.
Buoys have been placed where the future floating docks pilings are to be installed.
Commdive II has the first piling ready to go. All pilings have been moved from the parking lot to the wharf for easier installation.
Buoys have been placed where the future floating docks pilings are to be installed.